fbpx

What is Labor Efficiency Variance?

Labor Efficiency Variance

Share This...

Labor Efficiency Variance

Labor efficiency variance is a term used in managerial and cost accounting to measure the difference between the actual hours of labor needed to produce a good or perform a service and the standard or expected hours of labor. It is used to understand if the production process is efficient in terms of labor usage.

It is usually calculated using the following formula:

Labor Efficiency Variance = (Standard Hours – Actual Hours) x Standard Hourly Rate

If the actual hours are greater than the standard hours, then the variance is unfavorable because more time was spent on production than expected, leading to decreased efficiency. If the actual hours are less than the standard hours, then the variance is favorable because less time was spent on production than expected, leading to increased efficiency.

Keep in mind that while favorable variances are generally a good sign, they could also indicate potential issues, such as overestimation of standard hours or quality problems due to rushing. Likewise, unfavorable variances can highlight areas for improvement but could also be a sign of unrealistic standards or other underlying issues.

This metric is an important tool in variance analysis as it can help management understand where they may need to adjust processes, training, scheduling, and other factors to improve labor efficiency.

Example of Labor Efficiency Variance

Let’s consider a hypothetical scenario for a manufacturing company to illustrate how labor efficiency variance works:

Suppose ABC Manufacturing produces widgets. Their standard time for producing one widget is 2 hours. The standard pay rate for their workers is $20 per hour.

In a given month, ABC Manufacturing plans to produce 1,000 widgets. So, according to the standards, it should take 2,000 hours (1,000 widgets x 2 hours per widget) and cost $40,000 (2,000 hours x $20 per hour) in labor.

However, let’s say that due to various factors (e.g., machinery issues, worker inexperience), it actually took 2,100 hours to produce 1,000 widgets in that month. The actual labor cost is $42,000 (2,100 hours x $20 per hour).

Now, let’s calculate the labor efficiency variance:

Labor Efficiency Variance = (Standard Hours – Actual Hours) x Standard Hourly Rate Labor Efficiency Variance = (2,000 hours – 2,100 hours) x $20 per hour Labor Efficiency Variance = -100 hours x $20 per hour = -$2,000

The labor efficiency variance is -$2,000, which is unfavorable. This indicates that ABC Manufacturing used 100 hours more than expected to produce the 1,000 widgets, which resulted in an additional labor cost of $2,000.

This could prompt the company’s management to investigate why it took more time than expected to produce the widgets. The issue could be related to machinery, worker skills, or other factors, and identifying the cause could help improve efficiency in the future.

Other Posts You'll Like...

Want to Pass as Fast as Possible?

(and avoid failing sections?)

Watch one of our free "Study Hacks" trainings for a free walkthrough of the SuperfastCPA study methods that have helped so many candidates pass their sections faster and avoid failing scores...