What is Manufacturing Cycle Efficiency?

Manufacturing Cycle Efficiency

Share This...

Manufacturing Cycle Efficiency

Manufacturing Cycle Efficiency (MCE) is a measure that compares the time spent on value-added activities with the total lead time (or production cycle time) during a manufacturing process. This metric is crucial because it can identify areas of inefficiency or wasted time in the production process, providing valuable insights for performance improvement.

Value-added activities are the processes that directly contribute to the production of the final product and for which customers are willing to pay. These activities include tasks like assembling, machining, and inspecting the product.

Non-value-added activities are those that do not contribute directly to the production of the final product and do not enhance the product from the customer’s perspective. These activities might include waiting time, moving materials, or storing inventory.

The formula for Manufacturing Cycle Efficiency is:

MCE = Value-added time / Total production time

A higher MCE indicates a more efficient manufacturing cycle because a greater proportion of time is spent on value-added activities. Conversely, a lower MCE suggests there may be inefficiencies or non-value-added activities that could be minimized or eliminated to improve the manufacturing process.

Example of Manufacturing Cycle Efficiency

Suppose a furniture company produces custom tables. The production process involves several steps: designing the table, selecting and purchasing the raw materials, processing the materials, assembling the table, finishing (painting or varnishing), and then inspecting the finished product.

Now, let’s assume the total production time for a table (from the design phase to the final inspection) is 10 hours.

Out of these 10 hours:

  • 2 hours are spent on designing the table and purchasing materials,
  • 1 hour is spent moving materials around the factory and waiting for machines,
  • 5 hours are spent processing materials and assembling the table,
  • 1 hour is spent on finishing the table, and
  • 1 hour is spent on inspecting the final product.

In this scenario, the time spent on value-added activities would be the time for processing materials, assembling the table, finishing, and inspecting – a total of 7 hours.

Using the formula for Manufacturing Cycle Efficiency, which is Value-added time / Total production time, we would calculate the MCE as follows:

MCE = 7 hours (value-added time) / 10 hours (total production time) = 0.7 or 70%

This indicates that 70% of the total production time is spent on value-added activities, and there might be room for improvement in the process, particularly in reducing the non-value-added activities like moving materials around the factory and waiting for machines.