What is a Standard Labor Rate?

Standard Labor Rate

Share This...

Standard Labor Rate

A Standard Labor Rate is a predetermined cost or rate that represents the expected wage rate to be paid per hour of labor. In the context of standard costing and variance analysis, the standard labor rate is used to compare against actual wage rates to determine if a company is paying more or less for labor than expected.

This standard rate takes into account:

Once set, the standard labor rate is then used as a benchmark to:

  • Set Budgets: It aids in forecasting labor costs for future periods based on expected production levels.
  • Price Products or Services: Knowing the labor cost component can help in pricing decisions.
  • Variance Analysis: The difference between the actual labor rate and the standard labor rate can be analyzed to determine the labor rate variance.

The labor rate variance, in particular, is calculated as:

Labor Rate Variance = (Standard Labor Rate − Actual Labor Rate) × Actual Hours Worked

If the actual labor rate is higher than the standard rate, the variance will be unfavorable. Conversely, if the actual rate is lower, the variance will be favorable.

For example, if a company’s standard labor rate is $15 per hour, but they actually end up paying workers an average of $16 per hour for a certain job, there’s an unfavorable variance. If they used 100 hours of labor at this rate, the labor rate variance would be ($15 – $16) x 100 = -$100 unfavorable.

It’s essential for companies to periodically review and update their standard labor rates to ensure they reflect current market conditions, changes in benefits, and other factors affecting labor costs.

Example of a Standard Labor Rate

Let’s dive into a fictional scenario to understand the concept of a Standard Labor Rate and how it ties into variance analysis.

GreenGarden Inc. – Labor Rate Variance Calculation for Landscaping Services

Given Data:

  • Standard Labor Rate: GreenGarden Inc. has established a standard labor rate of $20 per hour for its landscapers. This rate is based on market surveys, and it includes wages, benefits, and other associated costs.
  • Actual Hours Worked: In a particular week, landscapers worked 150 hours on various projects.
  • Actual Total Labor Cost: GreenGarden Inc. paid a total of $3,300 to its landscapers for their work that week.

Step 1: Calculate Actual Labor Rate

Actual Labor Rate = Actual Total Labor Cost / Actual Hours Worked

Actual Labor Rate = $3,300 / 150 hours
Actual Labor Rate = $22 per hour

Step 2: Calculate Labor Rate Variance

Using the formula: Labor Rate Variance = (Standard Labor Rate − Actual Labor Rate) × Actual Hours Worked

Labor Rate Variance = ($20 – $22)x 150 hours
Labor Rate Variance = (-$2) x 150
Labor Rate Variance = -$300

Conclusion:

The labor rate variance of -$300 is unfavorable. This means GreenGarden Inc. paid $2 more per hour than they had anticipated based on their standard rate, resulting in an additional cost of $300 for the week.

To address this discrepancy, the management team at GreenGarden needs to investigate the reasons behind the higher labor costs. It could be due to overtime pay, the hiring of more experienced (and therefore more expensive) landscapers, or perhaps temporary wage increases. Additionally, it might be a sign that the standard labor rate needs updating to match current market conditions.